February in the spirit of light and choice

February
2026

February at Nová Myslivna follows the dynamic start of the new year. Construction works are progressing according to schedule, and the project is gradually moving into a phase where technical precision is being connected with the future appearance of the interiors.

While the installation of internal building systems, roof structures, and window assembly including HS portals is underway on site, future apartment owners still have the opportunity to select standards and request client modifications.

The building is closing in, the interior comes to life with light

The installation of aluminium windows and large-format lift-and-slide HS portals is one of the moments when the building undergoes a significant transformation. Interiors open up to natural daylight and the spaces begin to gain their true atmosphere.

The standard includes aluminium windows with insulating triple glazing, ensuring plenty of daylight along with high thermal and acoustic comfort. HS portals enable barrier-free access to a terrace or garden and highlight the modern architectural character of the building.

The quality of the indoor environment is further supported by external aluminium blinds, which will be part of the apartment equipment. They allow smooth light regulation, help maintain a comfortable indoor temperature, and at the same time preserve the clean appearance of the façade.

Time to decide

The possibility to adjust the final appearance of the apartments within the prepared standards as well as through individual changes remains open.

At the moment when technical layers are being completed and the building is gradually being enclosed, each apartment is gaining its personal character. Every choice – from surfaces to details – builds on the solid foundation that is now taking shape.

Nová Myslivna is thus entering the next stage with a clear direction: steady construction progress combined with space for individual decisions. February is not about visible changes at first glance – it is about quality, light, and the details that will shape the everyday comfort of future residents.

So you're not out of the loop

VIEW ALL NEWS

More than 1,000 combinations of tiles, flooring, and sanitary ware. Which one will be yours?

Nine natural stone décor options, five plaster-effect finishes, eight tap designs. Take a look at the philosophy behind how we, together with KERASERVIS, developed the interior tiles and sanitary solutions for Nová Myslivna.
February
2026

More than 1,000 combinations of tiles, flooring, and sanitary ware. Which one will be yours?

Nine natural stone décor options, five plaster-effect finishes, eight tap designs. Take a look at the philosophy behind how we, together with KERASERVIS, developed the interior tiles and sanitary solutions for Nová Myslivna.
February
2026

We are starting the New Year with full commitment and hard work

With the arrival of January, we are entering a new year that, for the Nová Myslivna project, is marked by the smooth continuation of construction works. While the calendar has turned to a new chapter, progress on site is certainly not slowing down – quite the opposite. The first weeks of the year confirm that the project is proceeding according to plan and moving into further key stages.
January
2026

We are starting the New Year with full commitment and hard work

With the arrival of January, we are entering a new year that, for the Nová Myslivna project, is marked by the smooth continuation of construction works. While the calendar has turned to a new chapter, progress on site is certainly not slowing down – quite the opposite. The first weeks of the year confirm that the project is proceeding according to plan and moving into further key stages.
January
2026

The Last Crane on Site

With December comes not only the end of the year, but also another milestone in the construction of the Nová Myslivna project. The build is progressing at a steady pace, and the past few weeks have brought a significant change worth noting.
December
2025

The Last Crane on Site

With December comes not only the end of the year, but also another milestone in the construction of the Nová Myslivna project. The build is progressing at a steady pace, and the past few weeks have brought a significant change worth noting.
December
2025

Moving into the Interiors

At the Nová Myslivna construction site, several important milestones have taken place over the past few weeks, allowing us to continue work inside the building at full intensity.
November
2025

Moving into the Interiors

At the Nová Myslivna construction site, several important milestones have taken place over the past few weeks, allowing us to continue work inside the building at full intensity.
November
2025

The call of the wild…

If you're interested in more information, leave us your contact details and we'll get back to you as soon as possible.