Construction work in October

October
2024

The foundation is the most important thing, and we’ve finished drilling and filling 220 posts with concrete. This is what Nová Myslivna will stand on. A quarter of the foundation slab is completed, and we’re working intensively on its remaining section.

Big changes also happened on the first basement floor, where the utility facilities pertaining to the wellness center have been installed. After careful waterproofing, we’re now fortifying this space. Another thing we’re currently working hard on is the precise placement of waste infrastructure.

Thanks to the amazing weather this month, construction work has been progressing by leaps and bounds. Here are the latest facts and figures fresh from the Nová Myslivna construction site.

220 posts
We drilled and filled with cement 220 foundation posts on which Nová Myslivna will stand. We took great care with the building’s foundation since we were dealing with very hard ground.

3,000+ m3 soil
Before Nová Myslivna can rise up, we needed to start underground. To get ready for construction, we removed over 3,000 m3 of soil.

45 people
This is the number of people who come to work at Nová Myslivna on a daily basis. Workers are currently focusing on the foundation slab and on the utility shaft for the future wellness zone.

2 cranes
We’ve temporarily changed Brno’s panorama. Two tall cranes now tower over Nová Myslivna, and two others will be added at a later date.

24 months
This is the amount of time we have to finish Nová Myslivna. In fall 2026, we’ll be handing over the first apartments to their new owners so they can enjoy the most beautiful views in Brno.

So you're not out of the loop

VIEW ALL NEWS

Nová Myslivna: The Last Crane on Site

With December comes not only the end of the year, but also another milestone in the construction of the Nová Myslivna project. The build is progressing at a steady pace, and the past few weeks have brought a significant change worth noting.
December
2025

Nová Myslivna: The Last Crane on Site

With December comes not only the end of the year, but also another milestone in the construction of the Nová Myslivna project. The build is progressing at a steady pace, and the past few weeks have brought a significant change worth noting.
December
2025

Nová Myslivna: Moving into the Interiors

At the Nová Myslivna construction site, several important milestones have taken place over the past few weeks, allowing us to continue work inside the building at full intensity.
November
2025

Nová Myslivna: Moving into the Interiors

At the Nová Myslivna construction site, several important milestones have taken place over the past few weeks, allowing us to continue work inside the building at full intensity.
November
2025

Nová Myslivna—Construction Is Reaching Its Highest Phase

We are currently finishing the top floor of the reinforced concrete structure, which also features the architectural highlight of the entire complex—a restaurant elegantly situated on the roof of the building. This striking part of the project hints at how unique the character of the entire place will be.
October
2025

Nová Myslivna—Construction Is Reaching Its Highest Phase

We are currently finishing the top floor of the reinforced concrete structure, which also features the architectural highlight of the entire complex—a restaurant elegantly situated on the roof of the building. This striking part of the project hints at how unique the character of the entire place will be.
October
2025

The Structural System is Almost Complete. Windows and Doors are Being Prepared.

The Nová Myslivna project is entering the phase in which its actual architecture is beginning to emerge from its shell. As the reinforced concrete skeleton grows and work begins on filling the building’s openings, i.e., windows and doors, the building is gradually taking on its future appearance.
September
2025

The Structural System is Almost Complete. Windows and Doors are Being Prepared.

The Nová Myslivna project is entering the phase in which its actual architecture is beginning to emerge from its shell. As the reinforced concrete skeleton grows and work begins on filling the building’s openings, i.e., windows and doors, the building is gradually taking on its future appearance.
September
2025

The call of the wild…

If you're interested in more information, leave us your contact details and we'll get back to you as soon as possible.

I am interested in
By submitting the form, I accept the personal data processing terms.
* Mandatory
Send
Your message was send
Sending failed. Please try again.