Construction work in October

October
2024

The foundation is the most important thing, and we’ve finished drilling and filling 220 posts with concrete. This is what Nová Myslivna will stand on. A quarter of the foundation slab is completed, and we’re working intensively on its remaining section.

Big changes also happened on the first basement floor, where the utility facilities pertaining to the wellness center have been installed. After careful waterproofing, we’re now fortifying this space. Another thing we’re currently working hard on is the precise placement of waste infrastructure.

Thanks to the amazing weather this month, construction work has been progressing by leaps and bounds. Here are the latest facts and figures fresh from the Nová Myslivna construction site.

220 posts
We drilled and filled with cement 220 foundation posts on which Nová Myslivna will stand. We took great care with the building’s foundation since we were dealing with very hard ground.

3,000+ m3 soil
Before Nová Myslivna can rise up, we needed to start underground. To get ready for construction, we removed over 3,000 m3 of soil.

45 people
This is the number of people who come to work at Nová Myslivna on a daily basis. Workers are currently focusing on the foundation slab and on the utility shaft for the future wellness zone.

2 cranes
We’ve temporarily changed Brno’s panorama. Two tall cranes now tower over Nová Myslivna, and two others will be added at a later date.

24 months
This is the amount of time we have to finish Nová Myslivna. In fall 2026, we’ll be handing over the first apartments to their new owners so they can enjoy the most beautiful views in Brno.

So you're not out of the loop

VIEW ALL NEWS

February in the spirit of light and choice

February at Nová Myslivna follows the dynamic start of the new year. Construction works are progressing according to schedule, and the project is gradually moving into a phase where technical precision is being connected with the future appearance of the interiors.
February
2026

February in the spirit of light and choice

February at Nová Myslivna follows the dynamic start of the new year. Construction works are progressing according to schedule, and the project is gradually moving into a phase where technical precision is being connected with the future appearance of the interiors.
February
2026

More than 1,000 combinations of tiles, flooring, and sanitary ware. Which one will be yours?

Nine natural stone décor options, five plaster-effect finishes, eight tap designs. Take a look at the philosophy behind how we, together with KERASERVIS, developed the interior tiles and sanitary solutions for Nová Myslivna.
February
2026

More than 1,000 combinations of tiles, flooring, and sanitary ware. Which one will be yours?

Nine natural stone décor options, five plaster-effect finishes, eight tap designs. Take a look at the philosophy behind how we, together with KERASERVIS, developed the interior tiles and sanitary solutions for Nová Myslivna.
February
2026

We are starting the New Year with full commitment and hard work

With the arrival of January, we are entering a new year that, for the Nová Myslivna project, is marked by the smooth continuation of construction works. While the calendar has turned to a new chapter, progress on site is certainly not slowing down – quite the opposite. The first weeks of the year confirm that the project is proceeding according to plan and moving into further key stages.
January
2026

We are starting the New Year with full commitment and hard work

With the arrival of January, we are entering a new year that, for the Nová Myslivna project, is marked by the smooth continuation of construction works. While the calendar has turned to a new chapter, progress on site is certainly not slowing down – quite the opposite. The first weeks of the year confirm that the project is proceeding according to plan and moving into further key stages.
January
2026

The Last Crane on Site

With December comes not only the end of the year, but also another milestone in the construction of the Nová Myslivna project. The build is progressing at a steady pace, and the past few weeks have brought a significant change worth noting.
December
2025

The Last Crane on Site

With December comes not only the end of the year, but also another milestone in the construction of the Nová Myslivna project. The build is progressing at a steady pace, and the past few weeks have brought a significant change worth noting.
December
2025

The call of the wild…

If you're interested in more information, leave us your contact details and we'll get back to you as soon as possible.

I am interested in
By submitting the form, I accept the personal data processing terms.
* Mandatory
Send
Your message was send
Sending failed. Please try again.