Construction work in February

February
2025

In a new video filmed at the construction site, the general contractor’s representative explains what rules builders are adhering to and what steps they take when the temperature drops below zero.

Frost isn’t an obstacle in construction if the right technological steps are taken. “Concreting is possible even at temperatures around −5°C if we follow the necessary measures and plan everything down to the last detail, including the timetable for concreting,” says Jan Ševčík, chief construction manager of BRESTT STAVBY a.s. 

The temperature of the formwork in which the concrete is poured shouldn’t fall below 1°C. It’s also necessary to ensure that snow and ice aren’t present in the structure. After the concrete mix is added, it’s essential that we keep the concrete temperature at least at 5°C. That’s why we carefully cover the entire structure and use hot air heaters to maintain the temperature within the required range,” he adds.

Watch the full video here.

So you're not out of the loop

VIEW ALL NEWS

Comfort and quality of living start from the moment you choose your home

Premium living is about more than the view, the quality of the materials or the services available to you. The buying experience itself matters just as much. How much do you need to pay upfront? When is the remaining balance due? And how much time do you have to arrange your financing? At Nová Myslivna, the process is designed to be straightforward. Once the apartment has been reserved, the buyer pays 20% of the purchase price. The remaining 80% is only due once the property has received its final approval and the apartment has been handed over. This means there is ample time between reserving the apartment and paying the remaining balance to arrange your financing well in advance.
September
2026

Comfort and quality of living start from the moment you choose your home

Premium living is about more than the view, the quality of the materials or the services available to you. The buying experience itself matters just as much. How much do you need to pay upfront? When is the remaining balance due? And how much time do you have to arrange your financing? At Nová Myslivna, the process is designed to be straightforward. Once the apartment has been reserved, the buyer pays 20% of the purchase price. The remaining 80% is only due once the property has received its final approval and the apartment has been handed over. This means there is ample time between reserving the apartment and paying the remaining balance to arrange your financing well in advance.
September
2026

August Brings Further Progress to the Façade

Construction of Nová Myslivna is progressing according to schedule, with new elements gradually being added to the building and shaping its final appearance. In recent weeks, the most noticeable changes have been taking place on the façade, while work on the terraces has also continued.
August
2026

August Brings Further Progress to the Façade

Construction of Nová Myslivna is progressing according to schedule, with new elements gradually being added to the building and shaping its final appearance. In recent weeks, the most noticeable changes have been taking place on the façade, while work on the terraces has also continued.
August
2026

What Lies Behind 13,000 m³ of Concrete?

13,000 m³ of concrete. It is a figure that is easy enough to read, but much harder to visualise. So what does that amount actually look like? Almost the same volume of concrete was used for the reinforced concrete foundation slab of the Burj Khalifa skyscraper. The figure of 13,000 therefore represents a scale that may not be immediately apparent when looking at a construction site. But the number itself tells only part of the story.
August
2026

What Lies Behind 13,000 m³ of Concrete?

13,000 m³ of concrete. It is a figure that is easy enough to read, but much harder to visualise. So what does that amount actually look like? Almost the same volume of concrete was used for the reinforced concrete foundation slab of the Burj Khalifa skyscraper. The figure of 13,000 therefore represents a scale that may not be immediately apparent when looking at a construction site. But the number itself tells only part of the story.
August
2026

July Sees Heat Pumps Installed on the Rooftops

Heat pumps take their place on the rooftops as interior works continue
July
2026

July Sees Heat Pumps Installed on the Rooftops

Heat pumps take their place on the rooftops as interior works continue
July
2026

The call of the wild…

If you're interested in more information, leave us your contact details and we'll get back to you as soon as possible.

I am interested in
By submitting the form, I accept the personal data processing terms.
* Mandatory
Send
Your message was send
Sending failed. Please try again.