Construction work in December

December
2024

Despite the winter weather, the concreting of the building's structure is continuing and at the end of December we almost finished the foundation slab.

"Even though the weather's been cold recently, our work on the building is continuing according to schedule. People in Brno have noticed that two additional cranes have been added to the site (we currently have four) and for a short time we even had up to five," says Project Leader Tomáš Tschöpl. The four cranes have for now become part of Masaryk Grove's and Kohoutovice's silhouette, which can be viewed from most places in Brno. Each shift at the construction site now numbers fifty workers on average. "Most of the work now consists of formwork, reinforcement, and concreting of the load-bearing part of the building. This entails other types of work such as waterproofing, radon venting, and earthing," adds Tomáš Tschöpl. 


What's almost finished is the foundation slab and builders are already concreting the ceilings of the first underground floor in a section of the future complex. What's emerging therefore is the ground floor of the residential section. "Technology allows us to concrete in cold weather down to five degrees celsius as long as we allow the concrete mix to hydrate before it freezes, which is easy for us to do," explains Tschöpl. 

An invisible yet important milestone is the completion of the sewerage system. A half-kilometer long connecting pipe will divert wastewater from Nová Myslivna to the Šárka Valley.

So you're not out of the loop

VIEW ALL NEWS

Nová Myslivna—Construction Is Reaching Its Highest Phase

We are currently finishing the top floor of the reinforced concrete structure, which also features the architectural highlight of the entire complex—a restaurant elegantly situated on the roof of the building. This striking part of the project hints at how unique the character of the entire place will be.
October
2025

Nová Myslivna—Construction Is Reaching Its Highest Phase

We are currently finishing the top floor of the reinforced concrete structure, which also features the architectural highlight of the entire complex—a restaurant elegantly situated on the roof of the building. This striking part of the project hints at how unique the character of the entire place will be.
October
2025

The Structural System is Almost Complete. Windows and Doors are Being Prepared.

The Nová Myslivna project is entering the phase in which its actual architecture is beginning to emerge from its shell. As the reinforced concrete skeleton grows and work begins on filling the building’s openings, i.e., windows and doors, the building is gradually taking on its future appearance.
September
2025

The Structural System is Almost Complete. Windows and Doors are Being Prepared.

The Nová Myslivna project is entering the phase in which its actual architecture is beginning to emerge from its shell. As the reinforced concrete skeleton grows and work begins on filling the building’s openings, i.e., windows and doors, the building is gradually taking on its future appearance.
September
2025

Securing a Mortgage for an Apartment in Nová Myslivna? Komerční Banka Offers Exceptional Services and Conditions

Premium apartments, premium services to help you purchase them. The Infinity Estate developer, together with Komerční banka, has prepared an advantageous mortgage rate and offers personal services for those interested in living in the unique Nová Myslivna complex in Brno.
August
2025

Securing a Mortgage for an Apartment in Nová Myslivna? Komerční Banka Offers Exceptional Services and Conditions

Premium apartments, premium services to help you purchase them. The Infinity Estate developer, together with Komerční banka, has prepared an advantageous mortgage rate and offers personal services for those interested in living in the unique Nová Myslivna complex in Brno.
August
2025

Construction of Nová Myslivna Proceeding Rapidly

Not even summer can slow down the fast tempo of work on the Nová Myslivna project, which is coming into clearer view every day. The construction site is now a lively hive of action and progress is visible on a daily basis. Our June important milestones are listed below.
July
2025

Construction of Nová Myslivna Proceeding Rapidly

Not even summer can slow down the fast tempo of work on the Nová Myslivna project, which is coming into clearer view every day. The construction site is now a lively hive of action and progress is visible on a daily basis. Our June important milestones are listed below.
July
2025

The call of the wild…

If you're interested in more information, leave us your contact details and we'll get back to you as soon as possible.

I am interested in
By submitting the form, I accept the personal data processing terms of Svoboda & Williams.
* Mandatory
Send
Your message was send
Sending failed. Please try again.