Concrete—the Star of the Show

March
2025

We asked Jan Ševčík, the main construction manager of BRESTT STAVBY a.s., the company that is creating Nová Myslivna, how work on it is going.

In December and January, work progressed from the underground floors to the above-ground ones and the structure is slowly but surely gaining in height. “We started working on Nová Myslivna in mid-September 2024 and we should be finished by the end of 2025,” says Jan Ševčík. “The total amount of concrete that the structure will need is roughly 14.500 m³. Our estimate of the total amount of reinforcement is 2,200 tons. We’re currently storing about 4,500 m³ of concrete and 750 tons of reinforcement, which is approximately 30–35% of the total volume,” he adds.

So you're not out of the loop

VIEW ALL NEWS

Nová Myslivna: The Last Crane on Site

With December comes not only the end of the year, but also another milestone in the construction of the Nová Myslivna project. The build is progressing at a steady pace, and the past few weeks have brought a significant change worth noting.
December
2025

Nová Myslivna: The Last Crane on Site

With December comes not only the end of the year, but also another milestone in the construction of the Nová Myslivna project. The build is progressing at a steady pace, and the past few weeks have brought a significant change worth noting.
December
2025

Nová Myslivna: Moving into the Interiors

At the Nová Myslivna construction site, several important milestones have taken place over the past few weeks, allowing us to continue work inside the building at full intensity.
November
2025

Nová Myslivna: Moving into the Interiors

At the Nová Myslivna construction site, several important milestones have taken place over the past few weeks, allowing us to continue work inside the building at full intensity.
November
2025

Nová Myslivna—Construction Is Reaching Its Highest Phase

We are currently finishing the top floor of the reinforced concrete structure, which also features the architectural highlight of the entire complex—a restaurant elegantly situated on the roof of the building. This striking part of the project hints at how unique the character of the entire place will be.
October
2025

Nová Myslivna—Construction Is Reaching Its Highest Phase

We are currently finishing the top floor of the reinforced concrete structure, which also features the architectural highlight of the entire complex—a restaurant elegantly situated on the roof of the building. This striking part of the project hints at how unique the character of the entire place will be.
October
2025

The Structural System is Almost Complete. Windows and Doors are Being Prepared.

The Nová Myslivna project is entering the phase in which its actual architecture is beginning to emerge from its shell. As the reinforced concrete skeleton grows and work begins on filling the building’s openings, i.e., windows and doors, the building is gradually taking on its future appearance.
September
2025

The Structural System is Almost Complete. Windows and Doors are Being Prepared.

The Nová Myslivna project is entering the phase in which its actual architecture is beginning to emerge from its shell. As the reinforced concrete skeleton grows and work begins on filling the building’s openings, i.e., windows and doors, the building is gradually taking on its future appearance.
September
2025

The call of the wild…

If you're interested in more information, leave us your contact details and we'll get back to you as soon as possible.

I am interested in
By submitting the form, I accept the personal data processing terms.
* Mandatory
Send
Your message was send
Sending failed. Please try again.