Concrete—the Star of the Show

March
2025

We asked Jan Ševčík, the main construction manager of BRESTT STAVBY a.s., the company that is creating Nová Myslivna, how work on it is going.

In December and January, work progressed from the underground floors to the above-ground ones and the structure is slowly but surely gaining in height. “We started working on Nová Myslivna in mid-September 2024 and we should be finished by the end of 2025,” says Jan Ševčík. “The total amount of concrete that the structure will need is roughly 14.500 m³. Our estimate of the total amount of reinforcement is 2,200 tons. We’re currently storing about 4,500 m³ of concrete and 750 tons of reinforcement, which is approximately 30–35% of the total volume,” he adds.

So you're not out of the loop

VIEW ALL NEWS

February in the spirit of light and choice

February at Nová Myslivna follows the dynamic start of the new year. Construction works are progressing according to schedule, and the project is gradually moving into a phase where technical precision is being connected with the future appearance of the interiors.
February
2026

February in the spirit of light and choice

February at Nová Myslivna follows the dynamic start of the new year. Construction works are progressing according to schedule, and the project is gradually moving into a phase where technical precision is being connected with the future appearance of the interiors.
February
2026

More than 1,000 combinations of tiles, flooring, and sanitary ware. Which one will be yours?

Nine natural stone décor options, five plaster-effect finishes, eight tap designs. Take a look at the philosophy behind how we, together with KERASERVIS, developed the interior tiles and sanitary solutions for Nová Myslivna.
February
2026

More than 1,000 combinations of tiles, flooring, and sanitary ware. Which one will be yours?

Nine natural stone décor options, five plaster-effect finishes, eight tap designs. Take a look at the philosophy behind how we, together with KERASERVIS, developed the interior tiles and sanitary solutions for Nová Myslivna.
February
2026

We are starting the New Year with full commitment and hard work

With the arrival of January, we are entering a new year that, for the Nová Myslivna project, is marked by the smooth continuation of construction works. While the calendar has turned to a new chapter, progress on site is certainly not slowing down – quite the opposite. The first weeks of the year confirm that the project is proceeding according to plan and moving into further key stages.
January
2026

We are starting the New Year with full commitment and hard work

With the arrival of January, we are entering a new year that, for the Nová Myslivna project, is marked by the smooth continuation of construction works. While the calendar has turned to a new chapter, progress on site is certainly not slowing down – quite the opposite. The first weeks of the year confirm that the project is proceeding according to plan and moving into further key stages.
January
2026

The Last Crane on Site

With December comes not only the end of the year, but also another milestone in the construction of the Nová Myslivna project. The build is progressing at a steady pace, and the past few weeks have brought a significant change worth noting.
December
2025

The Last Crane on Site

With December comes not only the end of the year, but also another milestone in the construction of the Nová Myslivna project. The build is progressing at a steady pace, and the past few weeks have brought a significant change worth noting.
December
2025

The call of the wild…

If you're interested in more information, leave us your contact details and we'll get back to you as soon as possible.

I am interested in
By submitting the form, I accept the personal data processing terms.
* Mandatory
Send
Your message was send
Sending failed. Please try again.